Follow this link to go to the text only version of nasa.gov
NASA - National Aeronautics and Space Administration
Follow this link to skip to the main content
+ Contact Us
+ Feedback

Go
BASICS Business Case News and Views IEMP in Practice

+ Home
What we've done
What we're doing
What we're planning
- August 2007
- June 2007
- May 2007
- April 2007
- March 2007
- February 2007
- January 2007

- December 2006
- November 2006
- October 2006
- September 2006
- August 2006
- July 2006
- June 2006
- May 2006
- April 2006
- March 2006
- February 2006
- January 2006

- Older Archives  Folder icon

+ Current Month



Monthly Highlights features a monthly IEMP update, including our progress, schedule information, upcoming activities and events in progress.


August 2007


IAM/PP&E Focused on Disposal Development

NASA’s Integrated Enterprise Management Program’s Integrated Asset Management (IAM) Project Property Plant and Equipment (PP&E) Module Project team has been focusing their energies on design and development this summer. With the start of August, the IAM/PP&E team wrapped up Sprint 7 while working hard to further the construction of the Disposal Solution, recently named DSPL. Sprint 8 picked up mid-month and continued the team’s focus on the development of DSPL. The Disposal feature will deliver main capabilities to the IAM/PP&E Project including:

  • Interface to GSA (General Services Administration) - estimated 96K records annually
  • Image Interface to GSA (currently 18K images annually, may increase 4x to full volume of records sent to GSA)
  • Interface from NSMS for OM&S (Operating Materials and Supply) disposal

The implications of these adjustments via the IAM/PP&E Project will mean changes for users who currently use NPDMS (NASA Property Disposal Management System) and will now use DSPL.

The IAM/PP&E team is also using the August time frame to gear up for a much anticipated project face-to-face meeting in Huntsville, Alabama next month. Individuals responsible for carrying out the implementation at all of NASA’s Centers will gather with the Agency Project Team for meetings and workshops designed to improve both implementation and business readiness efforts. This quarterly face-to face is scheduled for September 19-20, 2007.

Back to Top

""

 

 

 




+ USA.gov - The U.S. government's official web portal.
+ Freedom of Information Act
+ Budgets, Strategic Plans and Accountability Reports
+ The President's Management Agenda
+ Privacy Policy and Important Notices
+ Inspector General Hotline
+ Equal Employment Opportunity Data Posted Pursuant
to the No Fear Act

+ Information-Dissemination Priorities and Inventories
NASA - National Aeronautics and Space Administration
NASA Official: Gene Sullivan
March 2007
+ Contact NASA